Acquisition Planning Forecast System |
|
Forecast Record Number: | F2025071665 |
| Component: USCG/CG-SHORE | Published Date: Sept. 23, 2025, 12:22 p.m. | Previously Published On: Sept. 3, 2025, 3:15 p.m. |
| NAICS: 236220 - Commercial and Institutional Building Construction | Competition: YES |
| Small Business Set-Aside: N/A | Small Business Program: None |
| Contract Vehicle: Design/Build & Construction Services III (National) (NMACC III) | Contract Type: Firm Fixed Price |
| Contract Status: New Requirement | Anticipated Award Quarter: Q4 FY2026 |
| Estimated Solicitation Release: 2026-05-01 | Contract Complete: 2029-11-01 |
| Requirements Title: Kodiak Potable Water Distribution System Recapitalization | |
| Description: Design-Build project for potable water system improvements on Base Kodiak. Work includes the replacement of 2 existing potable water storage tanks (750,000-gallon and 250,000-gallon), approximately 8.25 miles of buried water mains, and water deluge system (which includes (2) – 300,000-gallon tanks and 1 mile of pipeline). | |
| Estimated Dollar Range: Over $100,000,000.00 | Place of Performance: Kodiak, AK |
| POC Name: Samantha Stoughtenger Bran | Alternate POC Name: |
| POC Phone: (571) 614-5654 | Alternate POC Phone: |
| POC Email: [email protected] | Alternate POC Email: |
| Small Business Specialist/APFS Coordinator POC Name: Cheryl Berry | |
| Small Business Specialist/APFS Coordinator POC Phone: (206) 815-5287 | Small Business Specialist/APFS Coordinator POC Email: [email protected] |
Change Log
| Field Changed | Old Value | New Value | Date Changed |
| Previous Published Date | None | 09/03/2025 | Sept. 23, 2025 |
| Published Date | 09/03/2025 | 09/23/2025 | Sept. 23, 2025 |
| Last Updated Date | 09/03/2025 | 09/23/2025 | Sept. 23, 2025 |
| Contract Complete | 10/15/2027 | 11/01/2029 | Sept. 23, 2025 |
| Requirement | Replacement of 2 existing potable water storage tanks (N9 - Nemetz tank, 750,000 gallons and N8 - Old Woman, 250,000 gallons) on BASE Kodiak. Existing welded steel ongrade tanks will be demolished and replaced with new ongrade tanks meeting seismic requirements and mixing/heating needs. | Design-Build project for potable water system improvements on Base Kodiak. Work includes the replacement of 2 existing potable water storage tanks (750,000-gallon and 250,000-gallon), approximately 8.25 miles of buried water mains, and water deluge system (which includes (2) – 300,000-gallon tanks and 1 mile of pipeline). | Sept. 23, 2025 |
| Requirements Title | Replace N8 and N9 Water Tanks (Kodiak) (MASI) (PN 30337056) | Kodiak Potable Water Distribution System Recapitalization | Sept. 23, 2025 |
| Estimated Solicitation Release | 08/01/2025 | 05/01/2026 | Sept. 23, 2025 |
| Award Quarter | Q1 2027 | Q4 2026 | Sept. 23, 2025 |
| Contract Vehicle | IDIQ TO/DO (Non Strategic Sourcing Vehicle Multiple Award Contract) | Design/Build & Construction Services III (National) (NMACC III) | Sept. 23, 2025 |
| Dollar Range | $20M to $50M | Over $100M | Sept. 23, 2025 |
| Small Business Program | TBD | None | Sept. 23, 2025 |