Acquisition Planning Forecast System

Forecast Record Number: 

F2025071665 Print

U.S. Department of Homeland Security
Component: USCG/CG-SHORE Published Date: Sept. 23, 2025, 12:22 p.m. Previously Published On: Sept. 3, 2025, 3:15 p.m.
NAICS: 236220 - Commercial and Institutional Building Construction Competition: YES
Small Business Set-Aside: N/A Small Business Program: None
Contract Vehicle: Design/Build & Construction Services III (National) (NMACC III) Contract Type: Firm Fixed Price
Contract Status: New Requirement Anticipated Award Quarter: Q4 FY2026
Estimated Solicitation Release: 2026-05-01 Contract Complete: 2029-11-01
Requirements Title: Kodiak Potable Water Distribution System Recapitalization
Description: Design-Build project for potable water system improvements on Base Kodiak. Work includes the replacement of 2 existing potable water storage tanks (750,000-gallon and 250,000-gallon), approximately 8.25 miles of buried water mains, and water deluge system (which includes (2) – 300,000-gallon tanks and 1 mile of pipeline).
Estimated Dollar Range: Over $100,000,000.00 Place of Performance: Kodiak, AK
POC Name: Samantha Stoughtenger Bran Alternate POC Name:
POC Phone: (571) 614-5654 Alternate POC Phone:
POC Email: [email protected] Alternate POC Email:
Small Business Specialist/APFS Coordinator POC Name: Cheryl Berry
Small Business Specialist/APFS Coordinator POC Phone: (206) 815-5287 Small Business Specialist/APFS Coordinator POC Email: [email protected]

Change Log

Field Changed Old Value New Value Date Changed
Previous Published Date None 09/03/2025 Sept. 23, 2025
Published Date 09/03/2025 09/23/2025 Sept. 23, 2025
Last Updated Date 09/03/2025 09/23/2025 Sept. 23, 2025
Contract Complete 10/15/2027 11/01/2029 Sept. 23, 2025
Requirement Replacement of 2 existing potable water storage tanks (N9 - Nemetz tank, 750,000 gallons and N8 - Old Woman, 250,000 gallons) on BASE Kodiak. Existing welded steel ongrade tanks will be demolished and replaced with new ongrade tanks meeting seismic requirements and mixing/heating needs. Design-Build project for potable water system improvements on Base Kodiak. Work includes the replacement of 2 existing potable water storage tanks (750,000-gallon and 250,000-gallon), approximately 8.25 miles of buried water mains, and water deluge system (which includes (2) – 300,000-gallon tanks and 1 mile of pipeline). Sept. 23, 2025
Requirements Title Replace N8 and N9 Water Tanks (Kodiak) (MASI) (PN 30337056) Kodiak Potable Water Distribution System Recapitalization Sept. 23, 2025
Estimated Solicitation Release 08/01/2025 05/01/2026 Sept. 23, 2025
Award Quarter Q1 2027 Q4 2026 Sept. 23, 2025
Contract Vehicle IDIQ TO/DO (Non Strategic Sourcing Vehicle Multiple Award Contract) Design/Build & Construction Services III (National) (NMACC III) Sept. 23, 2025
Dollar Range $20M to $50M Over $100M Sept. 23, 2025
Small Business Program TBD None Sept. 23, 2025